Major Projects Executed as of 25-May-2010 | Year | Contract Description | Work Location | Client | Main or S/ Contract | Value (UAE Dhs.) | From | To |
|---|
| 2010 | Asab Accommodation Facilities - Phase I | Asab | GASCO | Main | 144,274,473.20 | 12/Jul/07 | 15/Feb/10 | | 2008 | Zirku Production Facilities - Concrete Rehabilitation Phase - 8 | Zirku Island | ZADCO | Main | 26,741,582.60 | 05/Nov/06 | 09/Feb/09 | | 2008 | Zirku Production Facilities - Concrete Rehabilitation Phase - 1 | Arzanah Island | ZADCO | Main | 10,173,599.83 | 05/Nov/06 | 31/Dec/08 | | 2008 | Blast Proof Buildings at Das Island | Das Island | Adma-Opco | Main | 8,999,623.00 | 29/Aug/07 | 30/Nov/08 | | 2008 | Non Process Buildings at Habshan (C2904) | Habshan | GASCO | Main | 68,596,602.88 | 14/Aug/06 | 30/Jun/08 | | 2008 | Borouge 2 Project - Temporary Construction Facilities (C3021) | Ruwais | Tecnimont | Sub Contract | 26,741,582.60 | 26/Jul/07 | 28/Feb/08 | | 2007 | AGD-II Construction of Camp and Temporary Facilities (C2882) | Asab | Bechtel | Sub Contract | 102,894,446.28 | 24/Mar/06 | 31/Dec/07 | | 2007 | Civil Works for Gasco Asab and Bab ICS Project (C2751) | Asab , Bab | Cegelec | Sub Contract | 12,400,000.00 | 09/Mar/05 | 31/Aug/07 | | 2007 | Civil works for OGD-III Condensate storage Tanks. Subcontract # C286/4038 | Ruwais | NPCC / Takreer | Sub Contract | 40,518,791.51 | 10/Sep/05 | 15/May/07 | | 2007 | Civil works for Gasco Buhasa Facilities upgrading project (C2710) | Buhasa | Adyard | Sub contract | 9,759,659.87 | 20-Jul-04 | 31-Mar-07 | | 2006 | Gasco 3rd NGL Project at Ruwais - Site preparation works (GM1799) | Ruwais | CBI Eastern Anstalt
| Sub contract | 9,115,913.50 | 25-Aug-05 | 21-Feb-06 | | 2005 | Gasco 3rd NGL Train - Relocation of Existing Services (C2725) | Ruwais | GASCO | Main | 43,779,377.50 | 13-Oct-04 | 14-Jul-05 | | 2005 | Construction works for Shah Camp refurbishment and Asab CDS Foundation Repair (C2608) | Asab | ADCO | Main | 8,951,105.52 | 28-Apr-04 | 30-Jul-05 | | 2004 | Zirku Production Facilities - Rehabilitation of Concrete - Phase 7 (C2420) | Zirku Island | ZADCO | Main | 14,681,811.61 | 5-Jun-02 | 30-Aug-04 | | 2004 | Replacement of Hydroskimmer Pre-stressed concrete supply pipeline with RTRP (GRE) pipeline (C2587) | Ruwais | Takreer | Main | 13,923,189.00
| 30-Apr-03 | 23-Feb-04 | | 2003 | Construction and Operation of a Sewage Treatment Plant and Associated Works (C2253) | Das Island | Adma- Opco | Main | 55,853,090.00 | 23-Jan-01 | 31-May-03 | | 2003 | Coastal Protection Works at Flares Area (C2325) | Das Island | Adma- Opco | Main | 18,343,694.00 | 29-Jan-01 | 11-May-03 | | 2003 | COS Tank Bund Stabilization and Fire Water Drainage (C2460) | Das Island | Adma- Opco | Main | 12,869,562.00 | 9-Feb-02 | 9-Jun-03 | | 2003 | Unleaded Gasoline/Low sulphur Gas Oil Project, Takreer Ruwais | Ruwais | Technip- Conflexip | S/C | 12,968,077.30 | 15-Nov-02 | 15-Feb-03 | | 2002 | Construction of New Laboratory Building (C2356) | Ruwais | GASCO | Main | 7,734,312.00 | 1-Dec-00 | 31-Jan-02 | | 2001 | GASCO-Ruwais DCS Project (C2191) | Ruwais | GASCO/ U.T.S. Kent | Sub contract | 8,185,125.44 | 27-Apr-99 | 30-Nov-01 | | 2000 | Asab Gas Development Project | Asab | Snam-progetti | S/C | 238,225,000.00 | 1-Oct-97 | 30-Apr-00 | | 2000 | Zirku Production Facilities - Repair of Feed Surge and Emergency Crude Spheres Support Legs and Associated Concrete Repairs and Including Repair of Manholes (C.2137) | Zirku Island | ZADCO | Main | 12,516,829.00 | 26-Oct-98 | 25-Nov-00 | | 1999 | Civil Works Repair 1998 Package (C.2135) | Ruwais | GASCO | Main | 8,233,091.00 | 4-Mar-98 | 28-Jun-99 | | 1998 | Sahil Field Development Project - Civil Works (C.1976) | Sahil | Saipem/ ADCO | SC | 12,467,768.00 | 15-Mar-97 | 31-Mar-98 | | 1998 | Zirku Production Facilities - Concrete Repairs to 8 Nos. of Bridges, Zirku Island (C.2076) | Zirku Island | ZADCO | Main | 7,705,206.85 | 1-Aug-97 | 28-Oct-98 | | 1997 | Zirku Production Facilities - Concrete Repair to Sea water intake structures and associated pipe racks (C.1921) | Zirku Island | ZADCO | Main | 10,196,917.00 | 25-Jul-96 | 16-Nov-97 | | 1996 | Upgradation of Power Distribution Network in Liwa Area - Construction of 7 (Seven) Nos. 33 kv/ 11 kv Electrical Substations at different locations in Liwa Area (C.1757) | Liwa | WED/ Conspel - Emirates | SC | 21,000,000.00 | 25-Jan-95 | 24-Aug-96 | | 1996 | Upgradation of Power Distribution Network - Construction of 33 kv/ 11 kv Electrical Substations at Ghantoot and Medina Zayed (C.1584) | Ghantoot & Medina Zayed | WED/ CIVILCO | SC | 9,000,000.00 | 20-Apr-95 | 25-Jan-96 | | 1995 | Buhasa North Gas Injection Project (C.1599) | Buhasa | ADCO / Babcock | SC | 18,750,000.00 | 22-Feb-94 | 15-May-95 | | 1995 | Modics (A) -Field Installation Works (C.1746) | Das Island | ADMA- OPCO/ U.T.S. KENT | SC | 9,880,112.00 | 8-Oct-94 | 27-Apr-95 | | 1994 | Temporary Office Accommodation for 'H' Block Staff - ADCO West Compound Redevelopment- Abu Dhabi | Abu Dhabi | ADCO | Main | 8,262,540.00 | 3-Aug-93 | 31-Jan-94 | | 1994 | Modics project - Construction of Central Control Building & Three Local Equipment Rooms (C.1525) | Das Island | ADMA- OPCO | Main | 19,884,741.00 | 25-Jul-96 | 12-Dec-94 | | 1993 | GASCO Asab New Residential Complex Construction | Asab | GASCO | Main | 60,487,117.00 | 14-May-91 | 7-Apr-93 | | 1992 | Concrete Rehabilitation Project (CRP-Phase II) | Das Island | ADGAS | Main | 15,927,523.00 | 12-Jun-91 | 16-Aug-92 | | 1992 | Contract No. 188700/-943/3004- Sulphur - Handling Project - Civil Works | Ruwais | ADNOC | Main | 11,985,693.00 | 1-Jan-91 | 28-Feb-92 | | 1991 | Construction of additional facilities to Tarif Ammunition Stores | Tarif | UAE Armed Forces | Main | 52,316,769.00
| 21-Jan-90 | 17-Sep-01 | | 1983 | Construction of 150 Man Mess Blocks, Training Centre, Workshops and Sports Faciltieis | Bu Hasa | ADCO | Main | 39,923,403.84 | 1-Nov-81 | 30-Sep-83 | | 1982 | Construction of Station Roads Car Park and a Helipad | Asab | ADCO | Main | 10,109,439.00 | 24-Sep-81 | 23-Mar-02 | | 1981 | Construction of 52 Staff and 14 daily rate Accommodation Ancillary Works | Asab | ADCO | Main | 9,148,802.00 | 24-Jan-81 | 23-Nov-81 | 1981
| Minor Works | Asab/ Bu Hasa/ Al Ain | ADCO | Main | 10,552,630.00 | | | 1979
| Gas Treatment Plant | Habshan | ADNOC | Main | 9,101,337.70 | 1-Jan-79 | 1-May-79 |
|
|
|
|